Social Security Central Rules — cess payment and returns
Central · Requirement · Version 1
Checked extractOfficial source available
Applicability
Central Rules 41–44 Chapter VII cess process. State-authorised assessing officer, actual notified rate, local approvals and project facts must be verified; event-based return not a universal annual return.
Required documents
Self-assessment is certified by a chartered engineer; construction cost uses applicable State PWD/CPWD or other schedule rates or RERA documents for the commencement year, in Form XVI.
Form XV information to assessing officer within 60 days of work commencement or cess payment; changed information immediately and at latest within 30 days.
Advance cess at approval or before work begins; local-authority approval applications carry proof of online payment to the State Board. For projects longer than one year the proviso permits the first year assessed amount. Government/PSU bill deductions transfer within 30 days.
Form XVIII completion return to assessing officer within 60 days of each completed project; this event-based return is not an annual establishment return.
Assessment-order late payment attracts interest at 1% per month or part-month from the due date until payment; assessment penalties require notice and reasonable opportunity to be heard.
Central rules under the corresponding Code. Appropriate-government jurisdiction and each rule determine applicability; this is not a blanket substitute for state rules.
Captured statutory text, not a consolidated compliance opinion. Check the applicable section, appropriate government, commencement notification, amendments and state rules before applying it to an establishment. Activity field research remains incomplete.