Central construction sites: lighting and portable-lighting safeguards
Central · Requirement · Version 1
Checked extractOfficial source available
Applicability
Applies to building or other construction work where the Central Government is the appropriate Government under section 2(1)(d) of the Occupational Safety, Health and Working Conditions Code, 2020 (Code PDF p. 2). Rule 1(2) of the Central Rules provides for territorial extent throughout India.
Emergency lighting trigger
Where failure of artificial lighting would expose employees to risk, keep automatic emergency lighting of sufficient intensity in working condition, with energy sources independent of the general lighting installations.
Provide adequate and suitable lighting, including portable lighting where appropriate, at workplaces and other places employees may need to pass. The clauses cover areas close to workplaces, including utility service amenities, and areas where natural light is insufficient for safe working conditions.
Use portable electrical lighting cables of adequate size and characteristics for the power requirements and adequate mechanical strength for severe construction conditions.
Central rules under the corresponding Code. Appropriate-government jurisdiction and each rule determine applicability; this is not a blanket substitute for state rules.
Captured statutory text, not a consolidated compliance opinion. Check the applicable section, appropriate government, commencement notification, amendments and state rules before applying it to an establishment. Activity field research remains incomplete.
Occupational Safety, Health and Working Conditions Code, 2020
Ministry of Labour and Employment, Government of India
National statutory text concerning occupational safety, health and working conditions; establishment thresholds and sector provisions need section-level review.