Ports, harbors and dredging: September 2026 EC validity
Central · Requirement · Version 1
Checked extractOfficial source available
Applicability & limits
National EIA framework, limited to the identified provisions and source dates. Actual project sector, capacity, location, clearance conditions and competent authority must be checked. July compilation excludes OMs and defers to original Gazettes; later September ports changes are separately indexed. No complete October 2026 consolidation is claimed.
Applicability
The amendment covers ports, harbors, break waters and dredging, and removes them from the ten-year other-project group in paragraph 9(ii)(c).
The operative paragraph 9(iva) provides twenty years initial EC validity. Fifteen years in the recitals was an earlier recommendation, not the enacted duration.
An additional five years beyond twenty is conditional on EAC/SEAC examination of existing safeguards and incorporation of necessary additional EMP safeguards.
In deserving cases unable to become operational during the first extension, EAC/SEAC may examine and recommend another five years if appropriate, again reviewing safeguards/EMP. It is not an automatic thirty-year entitlement.
The amendment includes paragraph 9(iva) in the paragraph 9(v) extension-application provision. A particular delay condonation or transition decision is not supplied by this extract.
Amends paragraph 9 for ports, harbors, break waters and dredging: twenty-year validity and conditional extensions.
Operative amendment differs from fifteen-plus-five recommendations in the preamble. Publication is 21 September, not portal upload 22 September. No automatic project-specific expiry or retrospective extension is inferred.