Applicability & limits

National EIA framework, limited to the identified provisions and source dates. Actual project sector, capacity, location, clearance conditions and competent authority must be checked. July compilation excludes OMs and defers to original Gazettes; later September ports changes are separately indexed. No complete October 2026 consolidation is claimed.

Applicability

Obtain prior EC for listed new projects/activities and covered expansion, modernisation or changes in product/raw-material mix exceeding the relevant sector threshold. Prior EC is required before construction or land preparation, except securing the land; project-specific exemptions need separate review.

Source reference: EIA Notification: official consolidated text through July 2026 · p. 3; Paragraph 2(i),(ii); p. 3; Paragraph 2 opening

Project category

The Schedule separates Category A and B. Category B screening distinguishes B1, requiring an EIA report, from B2, not requiring that report. General Conditions and sector-specific notes can change appraisal level; no project category is assigned without its facts.

Source reference: EIA Notification: official consolidated text through July 2026 · p. 5; Paragraph 4(i); p. 7; Paragraph 7(i), screening

Authority

MoEFCC decides Category A on EAC recommendations; State/UT SEIAA decides covered Category B on SEAC recommendations, subject to General Conditions and specified Central-level exceptions. July 2026 SAEIA/SCEIA fallback applies when the State bodies are non-functional under the cited conditions.

Source reference: EIA Notification: official consolidated text through July 2026 · p. 5; Paragraph 4(ii),(iii); p. 6; Paragraph 4(iiia)
Additional source reference: EIA authorities: standing-authority amendment 2026 · p. 6; Paragraph 3(6b)

Application

After identifying prospective sites, submit prescribed Form 1 and applicable supplementary Form 1A, with a pre-feasibility report. Item 8 construction/area-development applications use a conceptual plan instead of that report. District minor-mineral Form 1M procedures are outside this extract.

Impact assessment

Prepare EIA/EMP against sector-specific standard ToR and additional specific ToR, if stipulated. B2 projects do not require scoping; B1 requires EIA. Appendix III sets the report structure, including baseline, impacts, mitigation, monitoring, studies and EMP.

Source reference: EIA Notification: official consolidated text through July 2026 · p. 8; Paragraph 7(i), scoping(ii),(vii); p. 7; Screening; p. 45; Appendix III; p. 46; Appendix III

Public consultation

Category A and B1 ordinarily require consultation: local public hearing and written stakeholder responses. Paragraph 7 lists specific exceptions, including B2 and eligible building/area-development projects. After consultation, address material concerns in final EIA/EMP or a supplementary report.

Source reference: EIA Notification: official consolidated text through July 2026 · p. 9; Paragraph 7(i), consultation(i); p. 10; Consultation(ii); p. 11; Consultation(vii)

Conditions

Appraisal recommends grant with stipulated terms/conditions or rejection with reasons. Apply the actual granted EC conditions; deliberate material concealment/false information can cause rejection or cancellation after personal hearing and natural justice.

Source reference: EIA Notification: official consolidated text through July 2026 · p. 11; Paragraph 7(i), appraisal(i); p. 14; Paragraph 8(vi)

Reporting

Submit soft-copy half-yearly compliance reports on the stipulated EC terms/conditions to the concerned regulatory authority on 1 June and 1 December each calendar year. Reports are public documents and the latest is displayed by the authority.

Source reference: EIA Notification: official consolidated text through July 2026 · p. 16; Paragraph 10(ii),(iii)

Source document

Official sources & provenance

EIA Notification: official consolidated text through July 2026

Ministry of Environment, Forest and Climate Change, Government of India

Verification
reviewed
Captured
05/10/2026
PDF SHA-256
55427a079aef97ef8264bb9876e9fb22945909d4608d28e701cf9e6840d0a37a
View official source ↗View captured PDF ↗

Official July 2026 compilation. Only the cited normal prior-clearance, appraisal, consultation, monitoring and validity provisions are checked. The original Gazettes prevail and OMs are not incorporated.

Portal upload was 23 July 2026; that is not a new Gazette publication or commencement date. September 2026 ports amendment is linked separately. District minor-mineral procedures, Appendix IX exemptions, violation/post-facto cases, court outcomes and every sector threshold are not consolidated by these extracts.

EIA authorities: standing-authority amendment 2026

Ministry of Environment, Forest and Climate Change, Government of India

Published
13 Jul 2026
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
ec5c5e5ab2f32197c3fb75a8ad38902e399af16f1480463f7d95120f70c014a2
View official source ↗View captured PDF ↗

Creates SAEIA/SCEIA fallback, changes institutional terms and removes automatic Central-level routing solely for absent SEIAA/SEAC.

Gazette header is 13 July; identifier generated 14 July and portal upload 16 July are distinguished. Selected paragraphs only; actual State authority functioning must be checked.