Environmental clearance: consultation and hearing evidence
Central · Requirement · Version 1
Checked extractOfficial source available
Applicability
National EIA framework, limited to the identified provisions and source dates. Actual project sector, capacity, location, clearance conditions and competent authority must be checked. July compilation excludes OMs and defers to original Gazettes; later September ports changes are separately indexed. No complete October 2026 consolidation is claimed.
Public consultation
Ordinarily combines district-wise local hearing at/near the site and written responses. SPCB/UTPCC conducts the hearing; separately check paragraph 7 exceptions for the project.
Request the Member Secretary of each concerned SPCB/UTPCC. Appendix IV specifies at least ten hard and equivalent electronic copies of draft EIA, including English and official-State/local-language summaries, with copies to the listed local authorities.
The board finalises hearing date/time/venue within seven days of draft-EIA receipt and advertises in a national and regional vernacular/official-language daily, allowing at least thirty days for public responses.
Videograph proceedings; record attendance, provide opportunities for questions, prepare agreed same-day signed minutes, and annex public issues/applicant responses in local/official language and English.
Proceedings are displayed locally and on the board website. Appendix IV describes hearing completion within forty-five days and forwarding within eight days of completion; the main paragraph also states forty-five-day forwarding. Both source wordings are retained here without computing a new combined deadline.
Official July 2026 compilation. Only the cited normal prior-clearance, appraisal, consultation, monitoring and validity provisions are checked. The original Gazettes prevail and OMs are not incorporated.
Portal upload was 23 July 2026; that is not a new Gazette publication or commencement date. September 2026 ports amendment is linked separately. District minor-mineral procedures, Appendix IX exemptions, violation/post-facto cases, court outcomes and every sector threshold are not consolidated by these extracts.