Lay-off: ChapterX prior-permission safeguards
Central · Requirement · Version 1
Applicability & limits
ChapterX specified factories, mines and plantations, excluding seasonal/intermittent establishments, with at least 300 workers or a higher number notified by the appropriate government on average per working day in the preceding 12 months; actual threshold notifications and facts require review.
Applicability
Section 77 requires at least 300 workers, or a higher notified threshold, on average per working day in the preceding 12 months; excludes seasonal/intermittent establishments. Its industrial establishment definition covers specified factories, mines and plantations.
Government permission
Prior permission is required for non-badli/non-casual workers on the muster roll. Exceptions: power shortage or natural calamity, and mine fire, flood, excess inflammable gas or explosion. Apply with reasons and simultaneously serve affected workers.
Mine continuation
For the listed mine emergencies, apply for permission to continue lay-off within 30 days after lay-off starts.
Decision period
Government non-communication within 60 days after an application results in deemed permission under section 78(5). A communicated order remains in force for one year, subject to review. This is not proof that any actual application has deemed approval.
Unapproved lay-off
Missing required permission application, untimely mine-continuation application or refusal makes lay-off illegal and preserves worker benefits as if no lay-off occurred. Exceptional government-order relief under subsection 9 is separate.
Compensation
Section 67 applies except its second proviso. The ChapterIX retrenchment/set-off proviso must not be automatically applied to ChapterX lay-off.
Alternative work
Under section 78 explanation the employer must consider the alternative work to need no special skill/previous experience and be work the worker can do, with normal wages offered. It must be in the same establishment or employer in the same town/village or a distance avoiding undue hardship. This test does not adopt section 69's fixed 8 km limit.
Official sources & provenance
Industrial Relations Code, 2020
Ministry of Labour and Employment, Government of India
- Published
- 29 Sept 2020
- Verification
- reviewed
- Captured
- 01/10/2026
- PDF SHA-256
- 43cadbd9ed08dd00dfba43571253eaf63d655f9fc411df5b9a1059de8d40ce09
View official source ↗View captured PDF ↗National statutory text addressing trade unions, industrial employment conditions and industrial disputes.
Captured statutory text, not a consolidated compliance opinion. Check the applicable section, appropriate government, commencement notification, amendments and state rules before applying it to an establishment. Activity field research remains incomplete.
Labour Codes — commencement notifications of 21 November 2025
Ministry of Labour and Employment, Government of India
- Published
- 21 Nov 2025
- Effective from
- 21 Nov 2025
- Verification
- reviewed
- Captured
- 01/10/2026
- PDF SHA-256
- 9a930647d6f4935b9b0761cef6c9aa0351f4b390339e3a948b1aba56939de627
View official source ↗View captured PDF ↗Original commencement instruments for the four Codes. The Social Security instrument must be read with the 19 December 2025 corrigendum and earlier commencement notifications.
National commencement evidence, not an establishment applicability determination. SS sections 17–141 commenced on 21 November 2025. Amendments to its sections 15,16 and164 entries are captured separately; do not use the uncorrected original list alone.
Industrial Relations Code amendment — February 2026
Ministry of Law and Justice, Legislative Department
- Published
- 16 Feb 2026
- Effective from
- 21 Nov 2025
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- 0fa0cba369edf54e9432d9851b9c326154a2b7965942b2e32412fc635b84aaa9
View official source ↗View captured PDF ↗Amends section 104(1) and inserts section 104(1A) of the Industrial Relations Code. Deemed effective 21 November 2025.
Original amendment Gazette, not a consolidated Code. Preserves functioning of existing Tribunals/statutory authorities until Code authorities become functional. Publication and assent are both 16 February 2026.