PESO pipeline prior approval — original FAQ document inventory
Central · Requirement · Version 1
Checked extractOfficial source available
Applicability
PESO pipeline prior-approval document inventory as stated in the original revised Petroleum Rules FAQ. Land-permission requirements differ between cross-country/interstate and CGD pipelines.
Prior-approval document inventory
Prior-approval document inventory
List position
Printed item
Document or drawing
1
a
Schematic drawing showing pipeline length and location/chainage of Dispatch Terminal, Receipt Terminal, Intermediate stations, major crossings and sectionalizing valve locations.
2
b
Route map on political or topographic map showing location/chainage of turning points, Dispatch Terminal, Receipt Terminal, Intermediate stations, major crossings and sectionalizing valve locations.
3
c
Layout of Dispatch station showing hook up location.
4
d
Layout of receipt station showing hook up location.
5
e
Piping and instrumentation diagram.
6
f
Intermediate stations layout showing pipeline.
8
h
EIA report and compliance of EIA recommendations.
9
i
QRA report and compliance of EIA recommendations.
10
i
HAZOP study report and compliance of EIA recommendations.
11
k
Copy of RoW/RoU notification.
12
l
Copy of permission from concerned authorities on whose land the pipeline is laid.
13
m
Copy of crossing permissions.
14
n
Detailed feasibility report and pipeline thickness calculation.
15
o
Methodology for corrosion protection.
16
P
Signed online application form.
17
q
Duly filled and signed Schedule-7.
18
r
PNGRB authorization copy for common carrier pipelines and CGD pipelines.
RoW/RoU notification from MoPNG under PMP Act, in the applicant company’s name. If laid in another company’s RoW/RoU, obtain sharing permission from MoPNG.
City Gas Distribution Network pipelines
Permission from authorities or land owners on whose land the pipeline is laid; submit a copy for approval.
PESO pipeline prior-approval and commissioning document lists and expressly stated submission/land-permission branches on pages 17–19.
The original FAQ is administrative guidance with no printed publication or commencement date. Both lists repeat item (i) and print EIA recommendations beside QRA and HAZOP reports; those words are retained without repair. This extract does not establish a universal MSIHC audit threshold, a 49-bar design pressure or complete current consolidation.