CETP members: pretreatment, flow data and discharge controls
Central · Requirement · Version 1
Checked extractOfficial source available
Applicability
CETP treated outlet under final Schedule I entry 55, effective 1 September 2025. Three discharge routes remain distinct. NS is absence of a specified value in this entry, not zero or unrestricted discharge. Stricter consent/Board standards and ZLD conditions can apply. Member PETP outlets and CETP inlet use separately specified Board/consent limits.
Discharge sources
Each member industry must use a single discharge point to the conveyance system leading to CETP.
Meet the PETP outlet norms in the member’s State Board/PCC consent. Pretreated effluent quantity and quality discharged to CETP must not exceed the Board/PCC specified limits.
Maintain leaking valves, cracked/fissured pipes and faulty equipment to avoid resource wastage and pollution; segregate, store and dispose of hazardous wastes from unit operations and primary treatment according to authorisation conditions.
CETP agencies may access member premises without prior notice to take wastewater samples and cross-check accessible OCEMS data. They must regulate member flows and take appropriate action for norm breaches or overdue agreed O&M contributions, including refusal of effluent or membership cancellation.
Final substitution of Environment (Protection) Rules Schedule I entry 55 for CETPs. Outlet routes and conditional relaxations are separate from Board-specific CETP inlet and individual PETP consent limits.
English text checked on PDF pp. 7–12. No universal standalone-industry or sewage-treatment-plant limits are inferred. Subsequent facility consent conditions, stricter Board standards and complete current-law consolidation remain separate. Environmental-clearance requirements are outside this extract.