CETPs: conditional COD and TDS relaxations

Central · Requirement · Version 1

Checked extractOfficial source available

Applicability

CETP treated outlet under final Schedule I entry 55, effective 1 September 2025. Three discharge routes remain distinct. NS is absence of a specified value in this entry, not zero or unrestricted discharge. Stricter consent/Board standards and ZLD conditions can apply. Member PETP outlets and CETP inlet use separately specified Board/consent limits.

Marine COD relaxation

A proper marine outfall is required and existing shore discharges must convert. The State Board may relax COD only where initial dilution is at least 150 times at discharge and at least 1,500 times 100 m away; maximum COD remains 500 mg/litre. This is conditional Board discretion, not the default sea limit.

Source reference: CETPs: final discharge standards and operating duties · p. 9; Note 2 marine outfall proviso

TDS relaxation bands

TDS relaxation bands
Member-industry intake-water TDSConditional maximum treated-outlet TDS
TDS ≤ 1,100 mg/litre2,100 mg/litre
1,100 < TDS ≤ 2,100 mg/litreIntake TDS + 1,000 mg/litre
TDS > 2,100 mg/litre3,100 mg/litre
Source reference: CETPs: final discharge standards and operating duties
PDF p. 9 · Full reference

p. 9; Note 2 TDS table

TDS authority and cap

Default TDS is 2,100 mg/litre. The concerned State Board/PCC may relax it where member-industry intake water exceeds 1,100 mg/litre, allowing a maximum contribution of 1,000 mg/litre with an absolute treated-outlet cap of 3,100 mg/litre. The table is conditional on that relaxation.

Source reference: CETPs: final discharge standards and operating duties · p. 9; Note 2 TDS proviso

Sewage mixing

For joint treated-effluent/sewage discharge on land, the State Board prescribes the mixing ratio. Board/PCC permission for sewage within CETP treatment requires improved biological treatability and design that accounts for both hydraulic and organic sewage loads.

Source reference: CETPs: final discharge standards and operating duties · p. 9; Note 3(1); p. 10; Note 4 State roles 11; p. 11; Note 4 State roles 11 continuation

Source document

Official sources & provenance

CETPs: final discharge standards and operating duties

Ministry of Environment, Forest and Climate Change, Government of India

Published
10 Sept 2024
Effective from
1 Sept 2025
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
20d4d6851434bde01a5f070077544a0fa6ce4e44ea858fd863b254888ddd3274
View official source ↗View captured PDF ↗

Final substitution of Environment (Protection) Rules Schedule I entry 55 for CETPs. Outlet routes and conditional relaxations are separate from Board-specific CETP inlet and individual PETP consent limits.

English text checked on PDF pp. 7–12. No universal standalone-industry or sewage-treatment-plant limits are inferred. Subsequent facility consent conditions, stricter Board standards and complete current-law consolidation remain separate. Environmental-clearance requirements are outside this extract.

Back to library records