National EIA framework, limited to the identified provisions and source dates. Actual project sector, capacity, location, clearance conditions and competent authority must be checked. July compilation excludes OMs and defers to original Gazettes; later September ports changes are separately indexed. No complete October 2026 consolidation is claimed.
Validity table
Validity table
Project class
Initial validity (years)
Conditional extension
River Valley, item 1(c)
13
Up to 2 years by authority
Nuclear power / nuclear fuel, item 1(e)
15
Up to 5 years by authority
Other projects, excluding mining and the separate September 2026 ports group
Validity runs from grant to production start, or completion of construction for item 8 projects. Mining validity is counted from mining-lease execution. This is not a statement that operating EC safeguards end when initial construction validity expires.
For the ordinary classes, apply in prescribed proforma to the authority within existing EC validity; the authority may consult the EAC. Item 8(b) ten-year validity covers the applicant-developer responsibilities only.
Approved/renewed mining-plan project life, capped at thirty years initially. An additional twenty years requires safeguards review every five years and timely proforma applications, limited by mining lease, mine life or fifty years, whichever is earlier.
The December 2022 OM states that ECs not expired on 12 April 2022, and ECs with extension applications submitted by that date under the notification, stand automatically extended to the 2022 increased validity. It does not revive every expired EC or establish an individual project expiry.
For ports, harbors, break waters and dredging use September 2026 paragraph 9(iva), not the old ten-year other-project entry. Actual transition/project conditions require separate assessment.
Ministry clarification of ECs unexpired or with extension applications submitted on 12 April 2022. Historical transition, not automatic revival of every expired clearance.
Table is the 2022 context. September 2026 separately changes ports, harbors, break waters and dredging.
Ports and harbors: environmental-clearance validity amendment 2026
Ministry of Environment, Forest and Climate Change, Government of India
Amends paragraph 9 for ports, harbors, break waters and dredging: twenty-year validity and conditional extensions.
Operative amendment differs from fifteen-plus-five recommendations in the preamble. Publication is 21 September, not portal upload 22 September. No automatic project-specific expiry or retrospective extension is inferred.