Kerala lifts and escalators - permit and licence service periods and documents

Kerala · Requirement · Version 1

Checked extractOfficial source available

Applicability

Entry 12 of Tables B and C added by SRO 112/2025: district offices of the Electrical Inspectorate, including the separately listed Ernakulam office. The stated periods are government working-day service-processing limits on the listed submissions, not licence validity or applicant filing deadlines. These source-specific extracts are limited to the Kerala lift/escalator regime. The original Act section 2(f) excludes a hoist or lift to which the Factories Act 1948 applies; no expansion of this literal exclusion to OSH Code equipment is inferred. The original Act scan is not a consolidated current-law review.

Government service periods

Government service periods
Notified serviceGovernment working daysSubmission and decision
Permit on application15On application: issue permit if in order; otherwise issue defect report.
Permit after rectifying defects10Issue permit on submission of compliance report after rectifying defects.
Inspection and initial licence10On completion report: conduct inspection and issue licence if installation is in order; otherwise issue defect report.
Licence after rectifying defects10Issue licence on submission of compliance report after rectifying defects.
Licence renewal10Issue licence on submission of licence-renewal application.
Source reference: Kerala lift and escalator permit and licence services - SRO 112/2025
PDF pp. 4–10 · Full reference

p. 4; Schedule Table B, entry 12(i); Working Days column; p. 5; Schedule Table B, entry 12(ii)-(iii); p. 6; Schedule Table B, entry 12(iv)-(v); p. 7; Schedule Table C, entry 12(i); p. 8; Schedule Table C, entry 12(ii); p. 9; Schedule Table C, entry 12(iii)-(iv); p. 10; Schedule Table C, entry 12(v)

Permit application documents

Permit application documents
DocumentNotified requirement
ApplicationForm A.
Drawings: copies and signaturesQuadruplicate copies signed by the applicant, authorised manufacturer signatory entrusted with lift/escalator erection, and licensed electrical contractor entrusted with electrical erection.
Schematic drawingLift/escalator installation including the earthing diagram.
Layout planPlan of erection with machine details.
Sectional elevationSectional elevation.
Passenger capacityPassenger capacity.
Building-plan approvalCopy of approval obtained from the concerned Local Body for the building plan.
Application-fee receiptOriginal challan receipt for each lift/escalator; paid into Government Treasury/FRIENDS under head of account 0043-00-102.
Source reference: Kerala lift and escalator permit and licence services - SRO 112/2025 · p. 4; Schedule Table B, entry 12(i)(a)-(b); p. 5; Schedule Table B, entry 12(i)(c)-(d); p. 7; Schedule Table C, entry 12(i)(a)-(b); p. 8; Schedule Table C, entry 12(i)(b)-(d)

Initial licence documents

Initial licence documents
DocumentNotified requirement
Completion intimation and licence applicationForm C.
Manufacturer work-completion reportForm D, obtained from the authorised lift/escalator manufacturer.
Completion reportForm E.
Licence-fee receiptOriginal challan receipt for each lift/escalator; paid into Government Treasury/FRIENDS under head of account 0043-00-102.
Owner insurance policyCopy of the policy taken by the owner covering the person using the lift/escalator.
Source reference: Kerala lift and escalator permit and licence services - SRO 112/2025 · p. 5; Schedule Table B, entry 12(iii)(a)-(b); p. 6; Schedule Table B, entry 12(iii)(c)-(e); p. 9; Schedule Table C, entry 12(iii)(a)-(e)

Renewal application documents

Renewal application documents
DocumentNotified requirement
Renewal applicationForm G.
Owner insurance policyCopy of the policy taken by the owner covering the person using the lift/escalator.
Renewal-fee receiptOriginal challan receipt for each lift/escalator; paid into Government Treasury/FRIENDS under head of account 0043-00-102.
Source reference: Kerala lift and escalator permit and licence services - SRO 112/2025 · p. 6; Schedule Table B, entry 12(v)(a)-(b); p. 7; Schedule Table B, entry 12(v)(c); p. 10; Schedule Table C, entry 12(v)(a)-(c)

Defect-rectification report signatories

For permit or licence after rectifying defects, the compliance report must be signed by the applicant, authorised manufacturer signatory entrusted with lift/escalator erection, and licensed electrical contractor entrusted with electrical erection.

Source reference: Kerala lift and escalator permit and licence services - SRO 112/2025 · p. 5; Schedule Table B, entry 12(ii); compliance report; p. 6; Schedule Table B, entry 12(iv); compliance report; p. 8; Schedule Table C, entry 12(ii); compliance report; p. 9; Schedule Table C, entry 12(iv); compliance report

Service and appellate authorities

Service and appellate authorities
RoleAuthority
Designated OfficerInspector
First Appellate AuthorityAdditional Chief Electrical Inspector
Second Appellate AuthorityChief Electrical Inspector
Source reference: Kerala lift and escalator permit and licence services - SRO 112/2025 · p. 4; Schedule Table B, entry 12; authority columns; p. 7; Schedule Table C, entry 12; authority columns

Original statutory lift exclusion

Original Act section 2(f) excludes a hoist or lift to which the Factories Act 1948 applies.

Source reference: Kerala Lifts and Escalators Act 2013 - original enacted Gazette · p. 15; original section 2(f); manually visually reviewed

Source document

Official sources & provenance

Kerala lift and escalator permit and licence services - SRO 112/2025

Government of Kerala, Power (C) Department

Published
31 Jan 2025
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
4ef33f269b648866aa515527e5a2a0f39f1e8b97c9327090394233c4f5a1906b
View official source ↗View captured PDF ↗

Final amendment to the Right to Service notification under section 3 of the Kerala State Right to Service Act 2012. Reviewed entry 12 of district Tables B and C: five lift/escalator permit, inspection, licence and renewal services, required documents, working-day service periods and designated/appellate authorities. Working-day periods are government service-processing times, not licence validity or applicant filing deadlines.

Original digitally signed Gazette No. 351 of 31 January 2025, captured unchanged. Native text and rendered Tables B/C on PDF pages 4-10 were compared. No fee amount, insurance-policy identifier, actual applicant details or licensing validity is supplied by these reviewed service rows.

Kerala Lifts and Escalators Act 2013 - original enacted Gazette

Government of Kerala, Law Department

Published
24 Apr 2013
Effective from
1 Mar 2012
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
93ee881eb773c4beec47bb642157ae0e06ec1969e4a647318f72e04bf3d24e6c
View official source ↗View captured PDF ↗

Original enacted Act. Reviewed only for identity, original deemed commencement and the literal section 2(f) exclusion of a hoist or lift to which the Factories Act 1948 applies. This scan is not a consolidated current Act; post-2013 amendments and OSH Code-transition applicability are not determined by this source.

Pinned original government scan. Gazette cover and English sections 1 and 2(f) were manually visually read on PDF pages 1, 14 and 15; the PDF uses two printed pages per image. Original annual licence validity and renewal filing periods are not represented as current.

Back to library records