PESO cross-country pipelines — original 2019 online-module procedure
Central · Requirement · Version 1
Checked extractOfficial source available
Applicability
Original September 2019 administrative direction concerning cross-country pipelines under Petroleum Rules, 2002/MSIHC Rules, 1989, with existing valid-PESO-permission and new-applicant branches kept distinct.
New entities seeking laying approval or commissioning permission
Register through the cited Apply Online application login and create a profile.
Existing approved/commissioned cross-country pipelines with valid PESO permission
Register/profile and apply online for revalidation to generate unique approval number and dockey; existing entities are advised to proceed on priority.
Heads of Circle Offices, Sub-circle Offices and NAPES&TS are advised to inspect cross-country pipelines within their inspection jurisdiction and advise approval holders to submit an online revalidation application in their inspection letter.
Original online laying/commissioning and revalidation route for cross-country pipelines, including existing valid PESO approvals, original 1 October 2019 mandatory-online date and advice to inspection offices.
The printed issue date is 19 September 2019, distinct from the 20 SEP 2019 stamp. No Gazette publication is shown. This is the original historical administrative instruction; it does not prove an unchanged present portal, prescribe a revalidation deadline or create an inspection frequency.