PESO pipeline commissioning — original FAQ document inventory

Central · Requirement · Version 1

Checked extractOfficial source available

Applicability

Original FAQ commissioning-document inventory. The 2025 circular permits considering commissioning without prior PESO inspection only for its specified minor modifications in approved Natural Gas CGD pipelines within a total 3 km; this is discretionary, with minor/major classification reserved to the Chief Controller of Explosives, Nagpur according to proposal complexity. Major modifications retain prior inspection.

Commissioning document inventory

Commissioning document inventory
List positionPrinted itemDocument or drawing
1aAs built schematic drawing showing pipeline length and location/chainage of Dispatch Terminal, Receipt Terminal, Intermediate stations, major crossings and sectionalizing valve locations.
2bAs built route map on political or topographic map showing location/chainage of turning points, Dispatch Terminal, Receipt Terminal, Intermediate stations, major crossings and sectionalizing valve locations.
3cAs built layout of Dispatch station showing hook up location.
4dAs built layout of receipt station showing hook up location.
5eAs built piping and instrumentation diagram.
6fAs built Intermediate stations layout showing pipeline.
7gAs built profile map.
8hEIA report and compliance of EIA recommendations.
9iQRA report and compliance of EIA recommendations.
10iHAZOP study report and compliance of EIA recommendations.
11kCopy of RoW/RoU notification.
12lCopy of permission from concerned authorities on whose land the pipeline is laid.
13mCopy of crossing permissions.
14nDetailed feasibility report and pipeline thickness calculation.
15oMethodology for corrosion protection.
16PSigned online application form.
17qDuly filled and signed Schedule-7.
18rDuly filled and signed Schedule-8.
19sIndependent Safety Audit report and compliance of recommendations.
20tPESO inspection report.
21uCopy of permission from M/oEF/SPCB/CRZ.
Source reference: PESO revised Petroleum Rules FAQ — pipeline application documents · p. 18; Question 2; complete 21-item commissioning list; inspection branch additionally qualified by 2025 circular
Additional source reference: PESO CGD pipeline approvals — original minor-modification circular, 11 September 2025 · p. 1; Original specified minor approved-CGD modifications only; retained major inspection; manually visually reviewed

Part-pipeline commissioning application

The FAQ permits applying for commissioning permission for part of the pipeline in the online module.

Source reference: PESO revised Petroleum Rules FAQ — pipeline application documents · p. 19; Question 11; application availability, not deemed permission

Source document

Official sources & provenance

PESO revised Petroleum Rules FAQ — pipeline application documents

Petroleum and Explosives Safety Organisation

Verification
reviewed
Captured
06/10/2026
PDF SHA-256
103d602311b65d010fb993a057d84cd2fc6307a52f1668da519f68a68a16f195
View official source ↗View captured PDF ↗

PESO pipeline prior-approval and commissioning document lists and expressly stated submission/land-permission branches on pages 17–19.

The original FAQ is administrative guidance with no printed publication or commencement date. Both lists repeat item (i) and print EIA recommendations beside QRA and HAZOP reports; those words are retained without repair. This extract does not establish a universal MSIHC audit threshold, a 49-bar design pressure or complete current consolidation.

PESO CGD pipeline approvals — original minor-modification circular, 11 September 2025

Petroleum and Explosives Safety Organisation; Chief Controller of Explosives, Nagpur

Verification
reviewed
Captured
06/10/2026
PDF SHA-256
970c8cf6dbfa1af2ae431ee4e8e0c6f61701b366d8b8c56bcad7707317ab74e0
View official source ↗View captured PDF ↗