Mounded and underground gas vessels: Schedule III inspection cycles
See applicability · Requirement · Version 1
Applicability
Applies only to compressed-gas pressure vessels, cryogenic vessels and ISO tank containers covered by the SMPV Rules under the Explosives Act 1884, subject to rule 2 definitions and rule 3 processing-plant exemptions. Air receivers, boilers, pressure piping, lifts and hoists are outside this excerpt. Read applicable LNG Schedule IV and hydrogen Schedule V in addition to these provisions; their full installation duties are not reproduced. Rules 18-20 and Schedule III have been reconciled against the seven final amendments through GSR 448(E) of 5 June 2026, checked 5 October 2026.
Schedule III inspection and test cycles
Mounded-vessel NDT scope
Ultrasonic thickness checks over the entire inner surface including dish ends/openings; 100% wet fluorescent magnetic-particle testing of weld joints; ultrasonic flaw detection of at least 25% of weld seams including specified T-joints, dish-end welds and nozzle joints; liquid-penetrant inspection of fillet welds/nozzle joints; random hardness testing as specified. Other established NDT techniques such as acoustic emission require prior Chief Controller approval.
Underground-vessel NDT scope
Ultrasonic thickness checks over the entire inner surface/openings; 100% wet fluorescent magnetic-particle testing of weld joints; ultrasonic flaw detection of all T-joints; liquid-penetrant inspection of all fillet welds and nozzle joints.
Underground multi-vessel installation
Conduct the rule 19 periodic tests so that both vessels are tested simultaneously, as stated in Schedule III B(15).
Annual monitoring
Monitor mounded-vessel/foundation settlement yearly. Monitor cathodic protection yearly and maintain records for both mounded and underground vessels.
Official sources & provenance
Static and Mobile Pressure Vessels (Unfired) Rules 2016
Government of India, Ministry of Commerce and Industry
- Published
- 1 Dec 2016
- Effective from
- 1 Dec 2016
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- 7f2d051591274c642cd6e2b45fad25985bac105247c61ad150054ebe129a39de
View official source ↗View captured PDF ↗Original final rules under sections 5 and 7 of the Explosives Act 1884. Reviewed extracts: rule 2 definitions and rule 3 exemptions; rules 6 and 18-20; Schedule III periodic inspection requirements. The original PDF is read with the separately attached final amendments; it is not a consolidated text.
Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.
SMPV final amendment - GSR 388(E)
Government of India, Ministry of Commerce and Industry
- Published
- 23 Apr 2018
- Effective from
- 23 Apr 2018
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- 2b7023780eb2608d7d2d2a70304018ac6bfa38e5b6571ac382ae380239a2876a
View official source ↗View captured PDF ↗Final amendment: rule 2 cryogenic definition wording, LNG provisions and substituted Schedule IV. Reviewed for its effect on the scope of rules 18-20 and Schedule III; additional LNG operational duties are outside these extracts.
Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.
SMPV final amendment - GSR 148(E)
Government of India, Ministry of Commerce and Industry
- Published
- 26 Feb 2019
- Effective from
- 26 Feb 2019
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- b7dbae23799629376bdb09322fccaa5e579bd655a0a5606270c498d715c99d41
View official source ↗View captured PDF ↗Final amendment to rule 47 concerning LS-1B. This original amendment is captured for the version chain; rule 47 was subsequently omitted by the 2026 amendment.
Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.
SMPV final amendment - GSR 609(E)
Government of India, Ministry of Commerce and Industry
- Published
- 1 Sept 2021
- Effective from
- 1 Sept 2021
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- 16a443ce09c613c9f209b109034bc3d1adfd8663d58db0a53b034a4aa3fb0a71
View official source ↗View captured PDF ↗Final amendment: substituted competent-person definition; ISO Tank Container and Third Party Inspection Agency definitions; TPIA references inserted in rules 18(2)(xiii), 19(1)(a) and 19(7). Earlier ISO transport forms and rule 47 wording are not represented as current.
Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.
SMPV final amendment - GSR 283(E)
Government of India, Ministry of Commerce and Industry
- Published
- 1 May 2025
- Effective from
- 1 May 2025
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- 2d2de87a92ea646c49577f3573831a97845e30a26407bab3aab8e3fabbec9d88
View official source ↗View captured PDF ↗Final amendment inserting inspection and testing fees in Schedule I Part C. Captured for amendment reconciliation only: Schedule I was subsequently substituted by the June 2025 amendment. No April fee is presented as current.
Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.
SMPV final amendment - GSR 374(E)
Government of India, Ministry of Commerce and Industry
- Published
- 6 Jun 2025
- Effective from
- 6 Jun 2025
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- b9a259e52821520f0c75b1469d373aff84a313599b4bfeb0950b7ecb8a33d67d
View official source ↗View captured PDF ↗Final amendment adding hydrogen definitions, super-insulated cryogenic tanks and Schedule V; substituting Schedule I and changing other licensing provisions. Reviewed for the scope of the rules 18-20 extracts. Full hydrogen or LNG installation compliance is outside this batch.
Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.
SMPV final amendment - GSR 422(E)
Government of India, Ministry of Commerce and Industry
- Published
- 27 Jun 2025
- Effective from
- 27 Jun 2025
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- 0910925eb997d9a4d20f931789097998d4396914f1ad9c5773ef5859dce78acc
View official source ↗View captured PDF ↗Final amendment: hydrogen design standards, cryogenic hydrogen valves under rule 18(6), hydrogen fitness-for-service proviso under rule 19(6), and transport code under rule 38(4).
Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.
SMPV final amendment - GSR 448(E)
Government of India, Ministry of Commerce and Industry
- Published
- 5 Jun 2026
- Effective from
- 5 Jun 2026
- Verification
- reviewed
- Captured
- 05/10/2026
- PDF SHA-256
- 46c4fcf389f97bd2866db397ec43fd434bb631aab9526348d51735d3e86cded9
View official source ↗View captured PDF ↗Final GSR 448(E), not the February 2026 draft: ISO tank above-ground anchoring, mounded-vessel grouping, omission of rule 47 and replacement ISO permissions/forms. Reviewed against rules 18-20 and Schedule III; no changes to the captured testing frequencies occur in this amendment.
Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.