Gas pressure vessels: testing and repair precautions

See applicability · Requirement · Version 1

Checked extractOfficial source available

Applicability

Applies only to compressed-gas pressure vessels, cryogenic vessels and ISO tank containers covered by the SMPV Rules under the Explosives Act 1884, subject to rule 2 definitions and rule 3 processing-plant exemptions. Air receivers, boilers, pressure piping, lifts and hoists are outside this excerpt. Read applicable LNG Schedule IV and hydrogen Schedule V in addition to these provisions; their full installation duties are not reproduced. Rules 18-20 and Schedule III have been reconciled against the seven final amendments through GSR 448(E) of 5 June 2026, checked 5 October 2026.

Periodic-test precautions

Periodic-test precautions
Stage / conditionRequired precautionRule
Before testingThoroughly clean and examine externally and, as practicable, internally for defects, corrosion and foreign matter. Take fire/explosion precautions when removing pyrophoric or spontaneously combustible sludge.20(i)
Degassing flammable/toxic/corrosive transport vesselsUse a gas-tanker degassing station or licensed premises with Chief Controller-approved evacuation/degassing facilities.20(ii)
After testingThoroughly dry internally; stamp tester identity and test date; keep a record of all tests.20(iii)
Failed hydraulic test or otherwise unsafe vesselDestroy or render unsuitable, with intimation to the Chief Controller.20(iv)
Source reference: Static and Mobile Pressure Vessels (Unfired) Rules 2016 · p. 91; rule 20(i)-(ii); p. 92; rule 20(iii)-(iv)

Repair approval and execution

Obtain prior Chief Controller / authorised Controller approval of repairs or modifications, procedure and execution method. Work follows the accepted design code, including NDT and pressure testing under stage-wise inspection by a recognised inspector. Replacement of fitments involving no heating is excepted.

Source reference: Static and Mobile Pressure Vessels (Unfired) Rules 2016 · p. 84; rule 6(1)

Pre-repair emptying and purge

Before repairs, additions or alterations, completely empty the vessel and purge with inert gas.

Source reference: Static and Mobile Pressure Vessels (Unfired) Rules 2016 · p. 84; rule 6(2)

Repair record and recommissioning

Maintain complete repair/addition/alteration records, make them available to the Chief Controller or authorised Controller, and obtain permission before recommissioning.

Source reference: Static and Mobile Pressure Vessels (Unfired) Rules 2016 · p. 84; rule 6(3)

Source document

Official sources & provenance

Static and Mobile Pressure Vessels (Unfired) Rules 2016

Government of India, Ministry of Commerce and Industry

Published
1 Dec 2016
Effective from
1 Dec 2016
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
7f2d051591274c642cd6e2b45fad25985bac105247c61ad150054ebe129a39de
View official source ↗View captured PDF ↗

Original final rules under sections 5 and 7 of the Explosives Act 1884. Reviewed extracts: rule 2 definitions and rule 3 exemptions; rules 6 and 18-20; Schedule III periodic inspection requirements. The original PDF is read with the separately attached final amendments; it is not a consolidated text.

Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.

SMPV final amendment - GSR 388(E)

Government of India, Ministry of Commerce and Industry

Published
23 Apr 2018
Effective from
23 Apr 2018
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
2b7023780eb2608d7d2d2a70304018ac6bfa38e5b6571ac382ae380239a2876a
View official source ↗View captured PDF ↗

Final amendment: rule 2 cryogenic definition wording, LNG provisions and substituted Schedule IV. Reviewed for its effect on the scope of rules 18-20 and Schedule III; additional LNG operational duties are outside these extracts.

Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.

SMPV final amendment - GSR 148(E)

Government of India, Ministry of Commerce and Industry

Published
26 Feb 2019
Effective from
26 Feb 2019
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
b7dbae23799629376bdb09322fccaa5e579bd655a0a5606270c498d715c99d41
View official source ↗View captured PDF ↗

Final amendment to rule 47 concerning LS-1B. This original amendment is captured for the version chain; rule 47 was subsequently omitted by the 2026 amendment.

Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.

SMPV final amendment - GSR 609(E)

Government of India, Ministry of Commerce and Industry

Published
1 Sept 2021
Effective from
1 Sept 2021
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
16a443ce09c613c9f209b109034bc3d1adfd8663d58db0a53b034a4aa3fb0a71
View official source ↗View captured PDF ↗

Final amendment: substituted competent-person definition; ISO Tank Container and Third Party Inspection Agency definitions; TPIA references inserted in rules 18(2)(xiii), 19(1)(a) and 19(7). Earlier ISO transport forms and rule 47 wording are not represented as current.

Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.

SMPV final amendment - GSR 283(E)

Government of India, Ministry of Commerce and Industry

Published
1 May 2025
Effective from
1 May 2025
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
2d2de87a92ea646c49577f3573831a97845e30a26407bab3aab8e3fabbec9d88
View official source ↗View captured PDF ↗

Final amendment inserting inspection and testing fees in Schedule I Part C. Captured for amendment reconciliation only: Schedule I was subsequently substituted by the June 2025 amendment. No April fee is presented as current.

Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.

SMPV final amendment - GSR 374(E)

Government of India, Ministry of Commerce and Industry

Published
6 Jun 2025
Effective from
6 Jun 2025
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
b9a259e52821520f0c75b1469d373aff84a313599b4bfeb0950b7ecb8a33d67d
View official source ↗View captured PDF ↗

Final amendment adding hydrogen definitions, super-insulated cryogenic tanks and Schedule V; substituting Schedule I and changing other licensing provisions. Reviewed for the scope of the rules 18-20 extracts. Full hydrogen or LNG installation compliance is outside this batch.

Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.

SMPV final amendment - GSR 422(E)

Government of India, Ministry of Commerce and Industry

Published
27 Jun 2025
Effective from
27 Jun 2025
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
0910925eb997d9a4d20f931789097998d4396914f1ad9c5773ef5859dce78acc
View official source ↗View captured PDF ↗

Final amendment: hydrogen design standards, cryogenic hydrogen valves under rule 18(6), hydrogen fitness-for-service proviso under rule 19(6), and transport code under rule 38(4).

Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.

SMPV final amendment - GSR 448(E)

Government of India, Ministry of Commerce and Industry

Published
5 Jun 2026
Effective from
5 Jun 2026
Verification
reviewed
Captured
05/10/2026
PDF SHA-256
46c4fcf389f97bd2866db397ec43fd434bb631aab9526348d51735d3e86cded9
View official source ↗View captured PDF ↗

Final GSR 448(E), not the February 2026 draft: ISO tank above-ground anchoring, mounded-vessel grouping, omission of rule 47 and replacement ISO permissions/forms. Reviewed against rules 18-20 and Schedule III; no changes to the captured testing frequencies occur in this amendment.

Official original Gazette bytes captured from PESO or eGazette. Printed Gazette issue dates are used for publication; notification signing dates and digital issue identifiers can differ. Review is limited to the stated extracts and their seven listed final amendments. No general factory-equipment or OSH rule applicability is inferred.

Back to library records